CRP 841 will overlay approximately 3.1 miles of Leclerc Road North. Connecting to the Phase 2 project, this work will extend the new surfacing along this corridor to 11.6 miles, or about 1/3 of the total length. Motorists can expect delays during this work, expected to begin in the summer of 2019. Project duration is anticipated to be 8 weeks.
Don Ramsey, P.E.
Project Engineer
George W. Luft
Design Engineer, Project Lead
Eric M. Roth, P.L.S.
Project Surveyor
- Email: publicworks4u [at] pendoreille.org
- Phone: 509-447-4513
- In Person: 625 W. 4th St. Newport, WA
Partners: WSDOT & County Road Administration Board along with Federal Highway Department
County Contribution (Estimated $)
Project Contract Amount- $951,000
Anticipated Project Start- Spring 2019
Anticipated Project Completion- Summer 2019
Contractor-Interstate Concrete and Asphalt
Project Timeline
- Bids received and project awarded late fall 2018
- Pre-Construction Meeting 3/2019
- Set to begin work 5/29/2019